- This event has passed.
Wilshire/Western Intersection Closure Webinar
January 25 @ 12:00 pm - 6:00 pm
Beginning the weekend of March 1 and continuing for up to four weekends (two contingency weekends), the design-builder will remove the concrete deck panels on Wilshire Bl between Western Av and Manhattan Pl. Wilshire Bl will be closed to through traffic during this work. Paving from Western Av to Manhattan Pl will occur the final weekend of work.
Ahead of this work, Metro’s Construction Relations team will host a briefing to discuss the anticipated timeline and impacts. The project team will be available to answer your questions.
The briefing will be recorded, and posted on the project website.
The event will take place online at https://bit.ly/3QQJymL